  Current Projects Minimize
 
 

2011 Distribution Division Construction Schedule 

CLEANING & LINING – (Contractor-Metra)

 

1)   Phase A:   Prospect St                                                 2,920’ of 6” C.I.P.                  5/23 thru 7/25

                                                                                                           

2)   Phase B:   Orange St                                                   2,920’ of 6” C.I.P.                  7/3 thru 8/20

 

3)   Phase C:    Belmont, Mead Hall Sts                              1,575’ of 6” C.I.P.                  8/21 thru 9/12

 

4)   Phase D:     Maryland and Wells                                   2,885’ of 6” C.I.P.                  9/13 thru 10/23

WATER MAIN CONSTRUCTION - by Manchester Water Works

 

1)  Ready St – N. River to Elm                                      350’ of 4” D.I.P.                          7/11 thru 7/20

           

2)  Dunbarton Rd D.O.L. – EnglishVillage westerly          6,600’ of 12” D.I.P.                      7/18 thru 11/11

 

3)  Mason St – Kimball St, westerly                              300’ of 6” D.I.P.                          11/14 -11/18  

 

4)  Large Valve Installation                                          2 Valves                                     Fall 2011  

        

ENGINEERING AND INSPECTION - MAIN EXTENSIONS

 1) South Gray Court                                                   170’ of 6” D.I.P.                          Summer 2011

 2) Sentinel Ct.                                                           850’ of 8” D.I.P.                          Summer 2011
 
 3) Old Bedford Road (Bedford)                                    1800’ of 12” D.I.P.                       Summer 2011
last changed 7/19/2011