Cemetery Brook Drain Tunnel Project Photos
Welcome to the photos page of the CBDT project website! Provided below are current photos showing the status of each of the major project locations, including the TBM Launch Zone, the Tunnel and each of the Drop Shafts. Located at the bottom of this webpage is "Beyond the Site" with status photos or images associated with design, planning, major project milestones and various construction aspects of the tunnel project.
Project Site Status Photos
Site 0 - Tunnel

The first drive for The Tunnel Boring Machine (TBM) a.k.a. "Granite Janet" continues to mine as it approaches the 500 foot mark. This photo was taken inside the TBM shield where the precast concrete segments are installed. A concrete segment is being hoisted and set into place to complete what is refered to as a "ring". Each row of 6 precast concrete segments makes up the 5 foot long ring.
Site 1 - Launch Zone (Queen City Ave. Bridge)

Materials, construction workers and supplies access the TBM through the launch zone. This includes concrete segments that make up the finished tunnel. Additionally, liquid grout and slurry are pumped to the TBM from plants located next to the launch zone. This photo shows construction of the grout and slurry plants, including enclosures, which will help protect the equipment from winter weather and cold temperatures.
Site 2 - Drop Shaft (DS) - 1 (Queen City Ave.)

As controlled blasting and support systems within Drop Shaft 1 are completed to reach the full vertical depth of 50 feet below ground, the blasting operations are shifted to complete a large horizontal hole that will connect the Drop Shaft to the future tunnel. This large hole is somewhat like a cave and is called an "adit". Once the adit is completely excavated, it is finished with permanent concrete. This photo shows the adit being finished with concrete placed on the floor and walls.
Site 3 - Drop Shaft (DS) - 2 (Union Street)

Once concrete for the adit at Drop Shaft 2 is complete, a pipe bend is installed and permanent concrete can be placed to create the finished structure that will allow stormwater to pass smoothly through from the Drop Shaft, into the adit and eventually to the Tunnel. The top part of this structure is called the "vortex structure". This photo shows steel reinforcement that is used to complete the permanent concrete floor of the vortex structure.
Site 4 - Drop Shaft (DS) - 3 (Beech Street)

Similar to construction at DS-2, once concrete for the adit at Drop Shaft 3 is complete, a pipe bend is installed and permanent concrete can be placed to create the finished structure that will allow stormwater to pass smoothly through from the Drop Shaft, into the adit and eventually to the Tunnel. This photo shows steel reinforcement that is used to complete the permanent concrete floor of the vortex structure for Drop Shaft 3.
Site 5 - Drop Shaft (DS) - 4 (Wilson Street)

Steel sheet piles are used for support of excavation (SOE) installation to hold the soil back within Drop Shaft 4 excavation. Once sheet piles are driven down to the top of bedrock depths, the soil can be safely removed and support bracing installed to stabilize the sheet piles. This photo shows how material is dug out from the inside of the SOE and removed. These excavations are so deep, it takes two machines to dig material down to bedrock levels. Once bedrock is exposed, controlled blasting operations can begin.
Site 6 - Drop Shaft (DS) - 5 (Taylor Street)

Installation of several tunnel vent shafts located at Drop Shaft 5 location near Taylor Street. Vents are drilled using a large diameter drill bit that comes in different sections (sometimes called "cans"). These large steel cans are in the forefront of this picture and connected to the drill rig. The drill rig pushes the cans into the ground to create an opening for the vent shaft piping. The auger on the end of the drill rig drills out dirt or rock and removes the material from the "can". Once complete, a permanent vertical pipe will be installed in the "can" to create the vent. These vents are used throughout the length of the tunnel to remove air as the tunnel fills with water during rain events.
Site 7 - Drop Shaft (DS) - 6 (Massabesic Street)

In order to start the design of sheet piles for the support of excavation (SOE) at DS-6, utilities and bedrock depths need to be determined. This photo shows a machine completing "pre-drilling", which will locate the top of bedrock or boulders underground. This machine will drill around the entire excavation zone for DS-6 and the information gathered will help design the steel sheets that make up the SOE. Like at other drop shaft locations, the SOE is a temporary measure that provides a safe excavation to drill and blast and install permanent drop shaft components during all aspects of contruction.
Site 8 - Drop Shaft (DS) - 7 (Mammoth Road)

Pressure testing of a water hydrant located in Mammoth Road for water supply at future location of Drop Shaft 7. The construction at each of the Drop Shafts requires a lot of water to complete the work. Each of the Drop Shaft locations for this project required special permission to connect to the water supply. The contractor typically uses a hydrant to supply construction water to the site. This test will confirm there are no leaks with the new hydrant installation.
Site 9 - Consolidation Drainage Piping (Union, S. Willow, Cilley)

Once the new 60-inch diameter drain piping is installed under Cilley Road, the pipe is covered with soil and the road surface is paved. This photo shows the installation of pavement on Cilley Road so that the work zone can be re-opened for safe travel. When completed, the new 60-inch drainage piping will carry stormwater from Cilley Road to the DS-2 location near Union St.
Site 10 - Supplemental Vent Shaft (SV) - 2 (Maple & Silver)

Like Site 4 above, the tunnel vent shaft (or supplemental vent) near Maple and Silver Street also requires ground improvements using "jet grouting" technology. Ground improvements are needed at several locations along the tunnel path. Once the jet grouting is complete, the site can be restored to original condition for next phases of construction. This photo shows placement of gravel to restore the site.
Site 11 - Tunnel Outfall Structure (Merrimack River)

When completed, the tunnel will connect to an outfall structure that will direct stormwater into the Merrimack River at a location under the Queen City Avenue Bridge. This structure will be constructed of placed concrete and will contain large blocks that will control stormwater flow velocity before draining into the river. Like some of the other Drop Shaft sites, steel "sheets" link together to create a temporary wall that hold back soil as the river bank is excavated, a.k.a Support of Excavation (SOE). Once excavation is complete, the foundation and outfall structure can be installed. This photo shows machinery removing soil from inside the completed SOE so that the bottom of the permanent outfall foundation can be started.
Site 12 - Area 8 Ground Improvement Zone (Lincoln Street)

Like Site 10 above, the tunnel path requires ground improvements using "permeation grouting" technology. This photo shows drilling machines that create holes in the soil so grout can be added deep underground. Unlike some locations that require improving the ground conditions by making soft ground hard for structure installation, this location is primarily grouted or "hardened" to provide what is called a "safe haven" for the TBM mining operation. Deep underground, the TBM will stop at this safe haven so maintenance on the machine can be safely completed, which sometimes includes changing cutterheads. This location was carefully selected for ground improvements based on where the tunnel travels from soft ground and into very hard bedrock.
Site 13 - Supplemental Vent Shaft (SV) - 1 (Beech & Shasta)

Like Site 8 and Site 10 above, tunnel vent shafts are needed along the length of the completed tunnel. This photo shows the very start of SV-1 construction, which is another vent shaft location located between DS-2 and DS-3 near Beech Street. The construction zone is being secured and prepared for construction to maintain a safe working area. As noted above, vents are used throughout the length of the tunnel to allow trapped air to escape from the the tunnel as it fills with water during rain events. Without proper venting, the tunnel could be damaged and once SV-1 is complete, a permanent vertical vent pipe will extent from the tunnel to the ground surface.
Previous Site Photo Links
Select the links below to view and download past project photos
September 2025
October 2025
November 2025
December 2025
January 2026
February 2026
March 2026
April 2026
May 2026
June 2026

CBDT Beyond the Site
This section includes major project milestones, TBM details, and miscellaneous photos of important project components that support the mining operation or major construction.
Project Milestone Photos

June 2026 - Delivery of two sections (sheilds) of the Tunnel Boring Machine arrive in Manchester from Germany (via Portsmouth, NH)

June 2026 - The Tunnel Boring Machine Arrives at the Launch Zone

June 2026 - The Tunnel Boring Machine Cutterhead Arrives at the Launch Zone

June 2026 - Placement of the Tunnel Boring Machine Front Shield into the launch zone excavation with members of the project team watching.

June 2026 - Drop Shaft 2 Rock Excavation is completed

June 2026 - The end of Drop Shaft 2 adit is completed. This rock face is the location that the DS-2 adit will connect to the tunnel, once the TBM mines past this location.

August 2026 - Once the TBM is assembled and before it begins mining, it is signed by members of the team. The TBM started mining in September of 2026.

September 2026 - Drop Shaft 1 Rock Excavation is completed.

September 2026 - Inspection of the Drop Shaft 2 Adit construction.

Tunnel Boring Machine (TBM) Photos

Tunnel Boring Machine cutterhead under fabrication in Germany

Tunnel Boring Machine interior with segment mold on conveyor, under fabrication in Germany

Tunnel Boring Machine interior behind the cutterhead, 16 cylinders that help push and drive, under fabrication in Germany

Tunnel Boring Machine interior precast concrete segment conveyor

Project Support Photos

Tunnel Segment Forms - Used to pour precast concrete tunnel liner segments at the remote production plant in Connecticut

Completed precast concrete tunnel segments - These pieces will be delivered from Connecticut to the launch zone site and stored until they are ready to be placed in the tunnel. These segments will be part of the finished tunnel walls.

Tunnel Boring Machine push frame design - Used at the start of the tunnel to push the tunneling machine into the ground

Tunnel Boring Machine push frame - The vertical section of the push frame assembly

Slurry plant installation at the Launch Zone. This plant is used to produce a thick liquid that will be pumped to the front of the Tunnel Boring Machine cutterhead. This slurry will support the excavated face of the tunnel and will also be used to carry the mined material from the tunnel back to the production plant.