Home » Departments » Sewer and Stormwater » Cemetery Brook Drain Tunnel Project » Project Progress Photos

Project Progress Photos

Cemetery Brook Drain Tunnel Project Photos

Welcome to the photos page of the CBDT project website! Provided below are current photos showing the status of each of the major project locations, including the TBM Launch Zone, the Tunnel and each of the Drop Shafts. Located at the bottom of this webpage is "Beyond the Site" with  status photos or images associated with design, planning, major project milestones and various construction aspects of the tunnel project.  

Project Site Status Photos

 

Site 0 - Tunnel

The photo shows a construction worker inspecting mechanical equipment and associated hydraulic connections inside an underground tunnel structure. Construction materials, tools, and insulation are visible on the work platform as crews perform installation and assembly activities.

The first drive for The Tunnel Boring Machine (TBM) a.k.a. "Granite Janet" continues to mine as it approaches the 500 foot mark. This photo was taken inside the TBM shield where the precast concrete segments are installed. A concrete segment is being hoisted and set into place to complete what is refered to as a "ring". Each row of 6 precast concrete segments makes up the 5 foot long ring. 

Site 1 - Launch Zone (Queen City Ave. Bridge)

The photo shows construction crews assembling a temporary wooden enclosure around mechanical equipment and piping in the launch zone as part of winterization activities. Workers are installing and securing the wood framing to protect the equipment from cold weather and winter conditions.

Materials, construction workers and supplies access the TBM through the launch zone. This includes concrete segments that make up the finished tunnel. Additionally, liquid grout and slurry are pumped to the TBM from plants located next to the launch zone. This photo shows construction of the grout and slurry plants, including enclosures, which will help protect the equipment from winter weather and cold temperatures.  

Site 2 - Drop Shaft (DS) - 1 (Queen City Ave.)

The photo shows an underground tunnel excavation with exposed rock surfaces and wire mesh reinforcement installed along the surrounding walls and ceiling. Orange spray-painted markings outline the proposed adit layout on the rock face, identifying the area for the planned excavation or opening.

As controlled blasting and support systems within Drop Shaft 1 are completed to reach the full vertical depth of 50 feet below ground, the blasting operations are shifted to complete a large horizontal hole that will connect the Drop Shaft to the future tunnel. This large hole is somewhat like a cave and is called an "adit". Once the adit is completely excavated, it is finished with permanent concrete. This photo shows the adit being finished with concrete placed on the floor and walls.  

Site 3 - Drop Shaft (DS) - 2 (Union Street)

The photo shows a deep, sheet-pile-supported excavation with internal steel bracing, temporary ventilation ducts, and utility piping in place. Crews are installing reinforcing steel at the bottom of the excavation in preparation for concrete placement for the vortex structure.

Once concrete for the adit at Drop Shaft 2 is complete, a pipe bend is installed and permanent concrete can be placed to create the finished structure that will allow stormwater to pass smoothly through from the Drop Shaft, into the adit and eventually to the Tunnel. The top part of this structure is called the "vortex structure". This photo shows steel reinforcement that is used to complete the permanent concrete floor of the vortex structure.  

Site 4 - Drop Shaft (DS) - 3 (Beech Street)

The photo shows ongoing construction of a reinforced concrete vortex structure within a deep excavation supported by steel sheet piling and heavy structural bracing. Crews are installing the dense reinforcing steel cage and associated formwork in preparation for concrete placement.

Similar to construction at DS-2, once concrete for the adit at Drop Shaft 3 is complete, a pipe bend is installed and permanent concrete can be placed to create the finished structure that will allow stormwater to pass smoothly through from the Drop Shaft, into the adit and eventually to the Tunnel. This photo shows steel reinforcement that is used to complete the permanent concrete floor of the vortex structure for Drop Shaft 3.     

Site 5 - Drop Shaft (DS) - 4 (Wilson Street)

The photo shows excavation work underway within a deep, steel sheet-pile-supported shaft, with internal structural bracing providing support to the excavation walls. Excavators are removing soil from the shaft as construction crews oversee the ongoing excavation and material removal activities.

Steel sheet piles  are used for support of excavation (SOE) installation to hold the soil back within Drop Shaft 4 excavation. Once sheet piles are driven down to the top of bedrock depths, the soil can be safely removed and support bracing installed to stabilize the sheet piles. This photo shows how material is dug out from the inside of the SOE and removed. These excavations are so deep, it takes two machines to dig material down to bedrock levels. Once bedrock is exposed, controlled blasting operations can begin.  

Site 6 - Drop Shaft (DS) - 5 (Taylor Street)

The photo shows a large drilling rig operating at the proposed ventilation shaft location, with drilling equipment positioned over the shaft excavation area. A construction worker is monitoring the drilling operations as crews perform shaft installation work.

Installation of several tunnel vent shafts located at Drop Shaft 5 location near Taylor Street. Vents are drilled using a large diameter drill bit that comes in different sections (sometimes called "cans"). These large steel cans are in the forefront of this picture and connected to the drill rig. The drill rig pushes the cans into the ground to create an opening for the vent shaft piping. The auger on the end of the drill rig drills out dirt or rock and removes the material from the "can". Once complete, a permanent vertical pipe will be installed in the "can" to create the vent. These vents are used throughout the length of the tunnel to remove air as the tunnel fills with water during rain events. 

Site 7 - Drop Shaft (DS) - 6 (Massabesic Street)

The photo shows pre-drilling operations for a ventilation shaft, with a large drilling rig positioned over a cylindrical casing installed in the ground. Additional casing sections and heavy equipment are staged nearby as crews prepare the site for shaft drilling activities.

In order to start the design of sheet piles for the support of excavation (SOE) at DS-6, utilities and bedrock depths need to be determined. This photo shows a machine completing "pre-drilling", which will locate the top of bedrock or boulders underground. This machine will drill around the entire excavation zone for DS-6 and the information gathered will help design the steel sheets that make up the SOE. Like at other drop shaft locations, the SOE is a temporary measure that provides a safe excavation to drill and blast and install permanent drop shaft components during all aspects of contruction. 

Site 8 - Drop Shaft (DS) - 7 (Mammoth Road)

Pressure testing of a water hydrant located in Mammoth Road for water supply at future location of Drop Shaft 7. The construction at each of the Drop Shafts requires a lot of water to complete the work. Each of the Drop Shaft locations for this project required special permission to connect to the water supply. The contractor typically uses a hydrant to supply construction water to the site. This test will confirm there are no leaks with the new hydrant installation. 

Site 9 - Consolidation Drainage Piping (Union, S. Willow, Cilley)

The photo shows crews paving a road, with an asphalt paver placing a fresh layer of asphalt along the roadway. Workers are using hand tools to spread and level the asphalt along the pavement edges to ensure a smooth, uniform surface.

Once the new 60-inch diameter drain piping is installed under Cilley Road, the pipe is covered with soil and the road surface is paved.  This photo shows the installation of pavement on Cilley Road so that the work zone can be re-opened for safe travel. When completed, the new 60-inch drainage piping will carry stormwater from Cilley Road to the DS-2 location near Union St. 

Site 10 - Supplemental Vent Shaft (SV) - 2 (Maple & Silver)

The photo shows a dump truck unloading jet grout spoils into a designated disposal pit while an excavator operates nearby. Crews are backfilling and managing the accumulated spoils as part of ongoing site restoration and construction activities.

Like Site 4 above, the tunnel vent shaft (or supplemental vent) near Maple and Silver Street also requires ground improvements using "jet grouting" technology. Ground improvements are needed at several locations along the tunnel path. Once the jet grouting is complete, the site can be restored to original condition for next phases of construction. This photo shows placement of gravel to restore the site. 

Site 11 - Tunnel Outfall Structure (Merrimack River)

The photo shows crews installing helical anchors along a supported excavation wall beneath an existing bridge structure. An excavator is positioned beside the timber lagging and steel support system while workers operate specialized equipment to secure the anchors and reinforce the excavation.

When completed, the tunnel will connect to an outfall structure that will direct stormwater into the Merrimack River at a location under the Queen City Avenue Bridge. This structure will be constructed of placed concrete and will contain large blocks that will control stormwater flow velocity before draining into the river.  Like some of the other Drop Shaft sites, steel "sheets" link together to create a temporary wall that hold back soil as the river bank is excavated, a.k.a Support of Excavation (SOE). Once excavation is complete, the foundation and outfall structure can be installed. This photo shows machinery removing soil from inside the completed SOE so that the bottom of the permanent outfall foundation can be started.  

Site 12 - Area 8 Ground Improvement Zone (Lincoln Street)

The photo shows crews operating a large drilling rig to install sleeve grout ports at the construction site. Workers are monitoring the drilling equipment and coordinating operations around the rig beneath the elevated industrial structure.

Like Site 10 above, the tunnel path requires ground improvements using "permeation grouting" technology. This photo shows drilling machines that create holes in the soil so grout can be added deep underground. Unlike some locations that require improving the ground conditions by making soft ground hard for structure installation, this location is primarily grouted or "hardened" to provide what is called a "safe haven" for the TBM mining operation. Deep underground, the TBM will stop at this safe haven so maintenance on the machine can be safely completed, which sometimes includes changing cutterheads. This location was carefully selected for ground improvements based on where the tunnel travels from soft ground and into very hard bedrock. 

Site 13 - Supplemental Vent Shaft (SV) - 1 (Beech & Shasta)

The photo shows crews setting up temporary construction fencing around the designated work area to secure the site and control access. Workers are positioning and aligning the fence panels along the perimeter as part of the initial site preparation activities.

Like Site 8 and Site 10 above, tunnel vent shafts are needed along the length of the completed tunnel. This photo shows the very start of SV-1 construction, which is another vent shaft location located between DS-2 and DS-3 near Beech Street. The construction zone is being secured and prepared for construction to maintain a safe working area. As noted above, vents are used throughout the length of the tunnel to allow trapped air to escape from the the tunnel as it fills with water during rain events. Without proper venting, the tunnel could be damaged and once SV-1 is complete, a permanent vertical vent pipe will extent from the tunnel to the ground surface. 

Previous Site Photo Links

Select the links below to view and download past project photos

September 2025
October 2025
November 2025
December 2025
January 2026
February 2026
March 2026
April 2026
May 2026
June 2026
 


 

CBDT Beyond the Site 

This section includes major project milestones, TBM details, and miscellaneous photos of important project components that support the mining operation or major construction. 

Project Milestone Photos

TBM_Shield_Deliveries_06.18.26

June 2026 - Delivery of two sections (sheilds) of the Tunnel Boring Machine arrive in Manchester from Germany (via Portsmouth, NH)

TBM_Delivery_06.18.26

June 2026 - The Tunnel Boring Machine Arrives at the Launch Zone

TBM_Cutter_Head_Delivery_06.18.26

June 2026 - The Tunnel Boring Machine Cutterhead Arrives at the Launch Zone

TBM_Front_Shield_Placement_06.18.26

June 2026 - Placement of the Tunnel Boring Machine Front Shield into the launch zone excavation with members of the project team watching.

Drop_Shaft_2_Completed_Rock_Excavation_06.15.26

June 2026 - Drop Shaft 2 Rock Excavation is completed  

Drop_Shaft_2_Tunnel_Adit_Connection_Point_06.15.26

June 2026 - The end of Drop Shaft 2 adit is completed. This rock face is the location that the DS-2 adit will connect to the tunnel, once the TBM mines past this location. 

TBM_Signing_Milestone_08.31.26

August 2026 - Once the TBM is assembled and before it begins mining, it is signed by members of the team. The TBM started mining in September of 2026. 

DropShaft_1 Completed_Rock Excavation_09.18.26

September 2026 - Drop Shaft 1 Rock Excavation is completed.

Drop_Shaft_1 Completed_Adit_Blasting_09.18.26

September 2026 - Inspection of the Drop Shaft 2 Adit construction.

Tunnel Boring Machine (TBM) Photos

TBM_Cutterhead

Tunnel Boring Machine cutterhead under fabrication in Germany

TBM_Interior_Segment_Conveyor_2

Tunnel Boring Machine interior with segment mold on conveyor, under fabrication in Germany

TBM_Rear_View_Interior_Main_Shield_Push_Jacks

Tunnel Boring Machine interior behind the cutterhead, 16 cylinders that help push and drive, under fabrication in Germany

TBM_Segment_Feeder

Tunnel Boring Machine interior precast concrete segment conveyor

Project Support Photos

Precast_Concrete_Tunnel_Segment_Forms

Tunnel Segment Forms - Used to pour precast concrete tunnel liner segments at the remote production plant in Connecticut

Tunnel_Precast_Concrete_Segments

Completed precast concrete tunnel segments - These pieces will be delivered from Connecticut to the launch zone site and stored until they are ready to be placed in the tunnel. These segments will be part of the finished tunnel walls. 

TBM_Push_Frame_Schematic

Tunnel Boring Machine push frame design - Used at the start of the tunnel to push the tunneling machine into the ground

Launch_Zone_TBM_Push_Frame_Assembly

Tunnel Boring Machine push frame - The vertical section of the push frame assembly 

Launch_Zone_TBM_Slurry_Production_Plant

Slurry plant installation at the Launch Zone. This plant is used to produce a thick liquid that will be pumped to the front of the Tunnel Boring Machine cutterhead. This slurry will support the excavated face of the tunnel and will also be used to carry the mined material from the tunnel back to the production plant.