CBDT Project Map and Photos

Welcome to the Cemetery Brook Drain Tunnel (CBDT)
Project Work Status Page!

This page is your window into one of Manchester’s largest infrastructure projects. Here, you can explore updates on construction progress and see how the CBDT team is advancing work beneath and around the City.

The map below highlights the tunnel alignment, including the Launch Trench and Drop Shafts (DS) 1 through 7. Beneath the map, you’ll find descriptions of ongoing activity at each location.

Curious about how it all works or looking to understand some technical terminology? We invite you to watch our project video on the homepage for an inside look at the engineering and innovation behind the Cemetery Brook Drain Tunnel.

Cemetery Brook Tunnel Status Map 

 

How to use map:

To access the legend: Click the box in the top left hand corner. To Zoom: Either use the scroll on your mouse, or click the +/- in the bottom right hand corner. To Pan: Click and drag the map. Basic Information: Click on any portion of the line to activate pop-up window. If the pop-up has arrows at the top left corner, use these to access more information.

Cemetery Brook Work Location and Work Status

Please refer to the "Project Progress Photos" link on the right side of this page for photos of the activities listed below. 

Tunnel 
  • Begin mining operations up to the CSX rail cooridor (approx St. 0+50) underway
Launch Site – Queen City Ave. Bridge
  • Installation of support gantries underway 
  • Delivery of precast concrete tunnel segments to TBM underway
  • Installation of concrete floor slabs and walls of the launch trench completed until full TBM is underground
  • TBM support utilities and systems for TBM operation completed
  • Commissioning of the muck handling system, water treatment plant and slurry plant completed
  • Installation of TBM staff offices and facilities completed
  • Placement of TBM and support gantries into the launch trench completed
  • Installation of push frame and working area for placement of the tunnel boring machine (TBM) in the launch trench completed
  • Installation of slurry plant for TBM operation completed
  • Support of excavation (SOE) construction completed
  • Excavation of Launch Trench completed
  • Ground improvements beneath the railroad crossing completed
Drop Shaft 1 – Intersection of Brown Ave. And Queen City Ave.
  • Controlled blasting of rock and rock removal to complete the horizontal adit underway
  • Controlled blasting of rock and placement of rock supports completed to bottom depth
  • Installation of vent shaft completed
  • Building demolition completed
  • Support of excavation (SOE) completed
Drop Shaft 2 – Between Union Street and Beech Street
  • Placement of drop tube that will connect the vortex structure to the adit structure underway
  • Placement of concrete for adit structure and de-aeration chamber completed
  • Controlled blasting for rock excavation completed
  • Rock excavation for adits (horizontal tunnels to connect drop shaft to tunnel) completed
  • Support of excavation (SOE) completed
  • Ground improvement work for tunnel completed
Consolidation Drain Pipe - Cilley Rd, S. Willow St, Queen City Ave & Union St
  • 60-inch drain pipe and manhole installations underway
  • Sewer lining work completed
  • Watermain relocation completed
Drop Shaft 3 – Near Somerville St. and Maple St.
  • Preparation for concrete placement of vortex structure underway
  • Placement of drop tube that will connect the vortex structure to the adit structure completed
  • Ground improvements for tunnel comlpeted
  • Controlled blasting for rock excavation completed
  • Support of excavation (SOE) completed
Supplemental Vent 2 - Near Maple St. and Silver St.
  • Preparation for ground improvements completed
  • Installation of vent shaft completed
Drop Shaft 4 – Near Wilson St. and Hayward St.
  • Installation of support of excavation and bracing underway
  • Preparation and pre-drilling for support of excavation (SOE) completed
  • Building demolition completed
  • Removal of site utilities completed
Drop Shaft 5 – Between Taylor St. and Cypress St.
  • Preparation and pre-drilling for support of excavation (SOE) underway
  • Drilling of vent shafts underway
  • Site clearing is completed
  • Site utility preparation is completed
Drop Shaft 6 – On Massabesic across from Elliot Hospital
  • Preparation and pre-drilling for support of excavation (SOE) underway
  • Relocation of utilities for completion of vent shaft and SOE installation underway
  • Drilling and installation of vent shaft underway
  • Site utility preparation completed
  • Building demolition completed
Drop Shaft 7 – On Mammoth Rd. at Rockingham Trail
  • Relocation of utilities for site access underway
  • Site utility preparation completed
Tunnel Outfall Structure - Merrimack River
  • Preparation of coffer-dam installation underway
  • Installation of sheet piles for support of excavation of the outfall structure underway underway
Entrance Box Culvert – On Rockingham Trail
  • Work to commence in 2028  
Tunnel Boring Machine (TBM)
  • Begin mining and routine maintenance of TBM underway
  • Connection of TBM support utilities completed
  • Connection of slurry plant and muck handling system to the TBM completed
  • Connection of TBM sections and support gantries completed
  • Delivery of TBM overland to the site completed
  • Delivery of support gantries (gear that follows the TBM into the tunnel) completed
  • Fabrication and shipment from Germany of TBM completed
  • TBM named by students at Hillside Middle School, refer to News and Publications page

TBM_Fabricated_In_Germany