2015 DISTRIBUTION DIVISION CONSTRUCTION SCHEDULE

WATER MAIN CONSTRUCTION - by Manchester Water Works

1) Wathern St, Bedford S River Rd Easterly 100' of 6" D.I.P. Completed
2) Goffe St - S. Main St to W Hancock St. 250' of 16" D.I.P. Completed
3) Head St - Varney St Northerly 1,000' of 6" D.I.P. Completed
4) Magnolia St - Ridge St to Robie St 700' of 8" D.I.P. 9/4 to 9/16
5) Hollis St - Elm St to Canal St 720' of 8" D.I.P. 8/24 to 9/3
6) Oakland St - Woodbine St to Orchard St 250' of 6" D.I.P. 9/17 to 9/22
7) Pennacook St - Pine to Union Sts 440 of 6" D.I.P 8/10 to 8/21
8) Richard St - Taylor St Westerly 310 of 4" D.I.P 9/23 to 9/30
9) High St - Chestnut to Union St 860 of 6" D.I.P Completed
10) Kelley St - Upland St Westerly 200 of 16" D.I.P 10/1 to 10/7
11) Worthle Rd Bedford - Constance St Westerly  170 of 8" D.I.P 10/8 to 10/14
12) System Wide Valve bolt replacement   5/1 to 11/30

Inspection Jobs

1) S River Rd - Colby Ct to Ridgewood Rd  1,400 of 12" D.I.P.       Completed
2) Elm St - Thayer St to Clark St 1,200 of 12" D.I.P. August
3) Cleaning and Lining - Various Locations 8,000' of 6" to 20" Completed
4) Lowell St - Chestnut St to Union St 900' of 12" D.I.P. 8/17 to 8/31

 

Meter Department

19) System Wide                                       Install Radio Reads        June - December    